The replacement of boilers at the University of Hull Applied Science Building involved the complex planning of works due to the boilers being located on the roof of the building and the pumps, plant and hot water plate located on the Ground Floor 4 storeys below. The £300’000 project involved crane lifts, complex BMS installations and was completed in the 10 week University shut down.

Location
University of Hull (Applied Science Department)
Client
Hull
Project
Boiler Installation